When Infrastructure Can’t Keep Pace: Financial Analysis of Digital Realty Trust’s California Data Center Portfolio and Covenant Implications
D.T. FranklyPublished:
Disclaimer: This article presents analysis based solely on publicly available information, raising questions warranting investigation by journalists, regulators, and institutional investors with appropriate resources and access. It makes no representations beyond what surfaces from examination of public documents. All covenant calculations represent hypothetical scenario modeling based on Q3 2025 SEC filings, not assertions about actual asset classifications or management decisions.
This analysis is not investment advice, financial guidance, or a recommendation regarding any securities. The author holds no position in DLR and is not making investment recommendations. Readers should consult qualified financial professionals before making investment decisions.
Summary
Digital Realty Trust (DLR), one of the world’s largest data center real estate investment trusts, operates multiple facilities across California’s most competitive markets. Recent developments in Santa Clara have brought attention to a broader pattern: data center construction proceeding ahead of available electrical infrastructure in California’s grid-constrained markets.
Documents reviewed for this analysis include:
- DLR’s Q3 2025 10-Q filing (October 31, 2025)
- Santa Clara building permits for 641 Walsh Avenue
- Silicon Valley Power capacity statements (November 2024)
- LADWP Scattergood modernization documentation
- News coverage from Bloomberg, Fortune, and Mercury News
Three facilities in DLR’s four-property California portfolio face documented power delivery constraints:
- SJC37 (Santa Clara): 430,000 sq ft completed building with no power until 2028 or later
- LAC10 (Downtown Los Angeles): 490,000 sq ft operational facility in service area of generator scheduled for 2029 shutdown
- LAX12 (El Segundo): Operating facility sharing western Los Angeles grid infrastructure
The covenant analysis examines DLR’s financial structure as disclosed in SEC filings. According to Q3 2025 data, DLR maintains $26.4 billion in unencumbered assets against $17.4 billion in unsecured debt, creating a coverage ratio of 1.52x—just 2% above the required 1.50x minimum. This narrow margin raises questions about classification practices for power-constrained facilities.
Background: California’s Grid Capacity Challenge
California data centers face infrastructure constraints unprecedented in their severity and duration. These constraints reflect broader challenges in upgrading electrical systems to meet exponentially growing power demands from artificial intelligence and cloud computing workloads.
Santa Clara Municipal Utility
Silicon Valley Power (SVP), Santa Clara’s municipal utility, operates a 700 MW grid currently delivering 420 MW to data centers—60% of total capacity. The city hosts 57 active data center facilities competing for limited power. Projected demand reaches 1,300 MW, nearly double current capacity.
In November 2024, SVP Chief Electric Utility Officer Manuel Pineda stated: “We’re getting close to reaching our system operating limit. [We] currently aren’t able to deliver power to every data center that wants to come to the city.” The utility projects system upgrades completion by 2028.
These timelines represent structural constraints, not administrative delays. Upgrading electrical infrastructure requires coordination across generation, transmission, and distribution systems, along with environmental reviews and construction of substations and transmission lines.
Los Angeles Department of Water and Power
Western Los Angeles faces a different constraint: the scheduled December 31, 2029 shutdown of Scattergood Generating Station under California’s Once Through Cooling regulations. The plant currently provides 284 MW of critical in-basin generation capacity.
LADWP is constructing a 330 MW hydrogen-ready combined-cycle replacement at an estimated cost of $800 million. The NREL analysis commissioned by LADWP identifies Scattergood as “the most immediate and instrumental location in relation to the requirement for firm (i.e., dependable) in-basin generation capacity due to the projected demand for energy in areas of the City that Scattergood serves.”
This creates a 2029 transition window where western Los Angeles—including downtown and El Segundo—will face generation capacity constraints during the switchover period.
Industry-Wide Challenges
These constraints are not unique to Digital Realty. Equinix, CyrusOne (before its 2022 acquisition), and other operators have reported similar challenges securing power commitments in California markets. The fundamental issue reflects California’s position at the intersection of aggressive renewable energy mandates, data center concentration, and grid modernization requirements.
California’s electrical infrastructure was designed for traditional commercial loads, not the concentrated, 24/7 power demands of modern hyperscale data centers. Adapting this infrastructure requires multi-year construction timelines that cannot be accelerated beyond physical and regulatory constraints.
Case Study: SJC37 Santa Clara Development Timeline
Digital Realty’s SJC37 facility at 641 Walsh Avenue provides a documented example of construction preceding power availability. The timeline reconstructed from public records demonstrates the duration and complexity of these challenges.
Construction Timeline
Santa Clara building permits document the development sequence:
- December 30, 2019: Building permit BLD2019-57176 filed for 641 Walsh Avenue
- 2020-2024: Construction period
- August 2024: Building permit status shows “Finaled,” indicating construction completion
- Current status: Building stands empty
- Power delivery: 2028 “at the earliest” per Silicon Valley Power statements
This creates a minimum nine-year timeline from permit application to potential energization, with six years of that period representing completed but unpowered building shell.
Physical Specifications
News coverage describes SJC37 as a 430,000 square foot, four-story structure designed for 48 MW critical IT load capacity according to DLR marketing materials. The facility represents substantial capital deployment in a market where power delivery remains uncertain.
Official Statements
In November 2025, DLR spokesman Jordan Sadler told Fortune magazine: “Sometimes we’re a little early. But we’re typically not late.” This statement acknowledges DLR’s practice of constructing facilities ahead of confirmed power availability.
The statement raises questions about development risk management. Typical real estate development practice involves securing utility commitments before beginning construction. The phrase “a little early” requires context: whether this refers to months, years, or—in SJC37’s case—a potential nine-year gap between permit and energization.
DLR VP of Data Center Portfolio Management Crystal Delany told Fortune that the facility could potentially be relocated, though the article notes this would be “expensive” and “is not typically done.” The technical feasibility and economic viability of relocating a completed four-story data center shell warrants further investigation.
News Coverage Context
Bloomberg reported in November 2025 that SJC37 has stood empty for six years, calculating from the 2019 permit date. The Mercury News noted that Silicon Valley Power cannot commit to power delivery timelines beyond “2028 at the earliest.”
These reports consistently cite the structural grid capacity constraints documented by Silicon Valley Power, not administrative delays or permitting issues. The utility’s statements make clear that power delivery awaits completion of system-wide infrastructure upgrades requiring multi-year construction timelines.
Covenant Analysis: Financial Structure and Scenario Modeling
DLR’s Q3 2025 10-Q filing discloses the company’s financial position and debt covenant requirements. This section presents objective scenario modeling based on those disclosures, examining how potential asset reclassifications would affect covenant compliance.
Current Financial Position (Q3 2025)
From the 10-Q filing:
- Total Assets: $48.7 billion (Page 5)
- Total Debt: $18.2 billion (Page 28)
- Unsecured Debt: $17.4 billion (Pages 28-29)
- Secured Debt: $826 million (Page 28)
- Development in Progress: $5.4 billion representing 6.5 million square feet (Pages 22, 50)
Unencumbered Asset Pool Calculation
DLR’s credit agreements require maintaining unencumbered assets at 150% of unsecured debt. The unencumbered asset pool represents total assets minus:
- Goodwill: $9.6 billion (Page 27)
- Intangible assets: $2.1 billion (Page 5)
- Secured collateral (estimated): $1.5 billion
- Joint venture equity investments: $3.7 billion (Page 25)
- Development portfolio: $5.4 billion (Pages 22, 50)
This calculation produces an estimated unencumbered asset pool of $26.4 billion. The required minimum (150% of $17.4 billion unsecured debt) is $26.1 billion.
Covenant Margin Analysis
Current position:
- Coverage ratio: 1.52x (actual unencumbered assets / unsecured debt)
- Required minimum: 1.50x
- Cushion: $300 million or 1.1% above required minimum
This narrow margin means a $300 million reduction in unencumbered assets would trigger covenant breach. The company also maintains leverage covenants requiring total debt not exceed 60% of total assets and secured debt not exceed 40% of total assets. The Q3 2025 position shows substantial headroom in these covenants.
Scenario Modeling
The following scenarios model potential impacts if power-constrained California facilities required asset reclassification or impairment recognition:
Scenario 1: Conservative ($500M reclassification)
- Assumption: Single major facility (e.g., Santa Clara campus)
- Unencumbered coverage: 1.49x
- Status: Breach (below 1.50x minimum)
- Required cure: $200 million asset addition or debt reduction
Scenario 2: Moderate ($1.0B reclassification)
- Assumption: Multiple facilities in power-constrained regions
- Unencumbered coverage: 1.46x
- Status: Breach (3.7% below minimum)
- Required cure: $643 million
Scenario 3: Severe ($2.0B reclassification)
- Assumption: Widespread California portfolio impact
- Unencumbered coverage: 1.40x
- Status: Breach (7.4% below minimum)
- Required cure: $1.49 billion
Cross-Default Provisions
DLR’s 8-K filing from September 30, 2024 documents cross-default provisions. A breach of the credit facility’s unencumbered asset covenant would trigger acceleration rights under the company’s senior notes, potentially requiring immediate repayment of the entire unsecured debt balance.
Classification Dynamics
The analysis raises questions about asset classification practices:
-
Operating vs. Development Status: How does DLR classify completed but unpowered facilities? If SJC37 remains in “development in progress” status, it excludes from occupancy calculations but stays in the unencumbered asset pool at full carrying value.
-
Impairment Recognition: At what point does extended power delay require impairment recognition? GAAP requires impairment when carrying value exceeds recoverable amount. For a facility with no power delivery commitment, determining recoverable amount presents challenges.
-
Market Value vs. Cost: Development in progress assets carry at cost. If market participants discount power-constrained facilities, should carrying values reflect this? The accounting framework provides flexibility in timing recognition.
Geographic Pattern: California Portfolio Composition
Digital Realty maintains four confirmed California facilities across two metropolitan areas, with three demonstrating power delivery constraints.
Silicon Valley (Santa Clara)
SJC37 (641 Walsh Avenue)
- Size: 430,000 sq ft
- Design capacity: 48 MW
- Status: Completed building, no power
- Timeline: 2028 or later power delivery
- Market context: SVP system at 60% capacity utilization, 57 facilities competing for power
SJC10 (1100 Space Park Drive)
- Status: Operational facility with existing power connection
- Represents DLR’s established presence in market
- No documented power constraints
Los Angeles Metro
LAC10 (600 West 7th Street, Downtown Los Angeles)
- Size: 490,000 sq ft
- Estimated capacity: 27-30 MW
- Status: Currently operational
- Future constraint: Western LA grid dependent on Scattergood station scheduled for 2029 shutdown
- Transition risk: LADWP replacement plant construction timeline
LAX12 (2260 E El Segundo Blvd, El Segundo)
- Status: Operational
- Grid exposure: Shares western Los Angeles infrastructure with LAC10
- Same 2029 transition constraints
Pattern Observations
Three of four California facilities face documented power constraints:
- One facility (SJC37): Complete power delivery failure, 6+ year delay
- Two facilities (LAC10, LAX12): Future constraint from 2029 grid transition
- One facility (SJC10): Normal operations with existing connections
This geographic concentration—75% of the California portfolio—in the state’s two most capacity-constrained utility service areas is statistically notable. Site selection targeting Santa Clara (where SVP explicitly states inability to deliver power to new facilities) and western Los Angeles (facing scheduled 2029 generation shutdown), followed by construction proceeding ahead of confirmed power availability, suggests either systematic due diligence failure or calculated acceptance of development risk that has materially manifested.
Neither explanation is fully consistent with the sophistication level expected of a major REIT operator. If due diligence identified these power constraints before construction, proceeding regardless requires economic justification not evident in public filings. If due diligence failed to identify these constraints, the failure occurred across multiple facilities in multiple markets over multiple years. Alternative explanations:
- Timing factors: Facilities may have been developed before grid constraints became apparent
- Market positioning: California markets command premium pricing that justifies development risk
- Future planning: DLR may anticipate grid improvements before operational impacts materialize
- Portfolio strategy: Company may accept California constraints as industry-wide challenge affecting all operators
None of these alternatives fully reconcile the timeline evidence (SJC37 permit filed December 2019, six years later still no power, utility stating 2028 “at earliest”) with standard real estate development practice of securing utility commitments before construction. The pattern warrants further investigation by parties with access to internal planning documents and decision-making records.
Disclosure Analysis: Public Information Availability
This section examines what information DLR has publicly disclosed about power-constrained facilities versus what remains undisclosed.
Disclosed Information
SEC Filings:
- Q3 2025 10-Q reports $5.4 billion in “development in progress” representing 6.5 million square feet
- Development portfolio disclosed in aggregate, not facility-by-facility breakdown
- Financial statements show covenant compliance calculations
- No specific disclosure of power delivery constraints by facility or market
Corporate Communications:
- DLR spokesman statements to media acknowledge construction ahead of power availability
- Marketing materials for SJC37 list 48 MW capacity without noting power unavailability
- Quarterly earnings calls (not reviewed for this analysis) may contain management commentary
Third-Party Sources:
- Municipal building permits provide construction timeline documentation
- Utility statements document grid constraints
- News coverage provides facility-specific details
- Industry databases list facility specifications
Information Gaps
Several key pieces of information remain undisclosed or unclear:
-
Facility-Level Carrying Values: The $5.4 billion development portfolio includes properties across multiple markets. SJC37’s specific carrying value does not appear in public filings. At 430,000 sq ft from a 6.5 million sq ft portfolio (6.6%), proportional allocation suggests approximately $336 million, but actual capitalized costs may differ significantly.
-
Power Delivery Contracts: Whether DLR holds contractual commitments from Silicon Valley Power for future power delivery, or whether 2028 represents an estimate without binding agreement, remains unclear from public documents.
-
Impairment Assessments: SEC filings do not disclose specific assets under impairment review or management’s assessment of recoverability for power-constrained facilities.
-
Alternative Plans: Whether DLR is actively pursuing facility relocation, sale, or other alternatives for SJC37 and what costs such alternatives would entail.
-
LA Transition Planning: How DLR plans to address the 2029 Scattergood transition for LAC10 and LAX12, including backup power, alternative grid connections, or customer notification procedures.
Disclosure Requirements
Public companies must disclose material information that reasonable investors would consider important in making investment decisions. Questions arising from this analysis:
- At what point does a multi-year power delay become material enough to require facility-specific disclosure?
- Should investors receive notification of geographic concentration risk in grid-constrained markets?
- Do power constraints affect asset classification for covenant calculation purposes?
- When must potential impairments be disclosed versus when formal impairment charges must be recognized?
These represent areas where additional disclosure could provide investors with information useful for assessing risk and valuation.
Industry Context: Regulatory Framework and Peer Practices
Data center development faces increasingly complex regulatory and infrastructure challenges across all markets, not just California. Understanding industry-wide practices provides context for DLR’s situation.
Regulatory Requirements
CPUC Rule 21 establishes interconnection procedures for facilities connecting to California’s electrical grid. The rule provides process but cannot override physical capacity constraints. When utilities reach system limits, interconnection timelines extend regardless of regulatory framework.
Environmental Review: California Environmental Quality Act (CEQA) requirements apply to major utility infrastructure projects. Grid expansion projects require environmental impact reports, public comment periods, and regulatory approvals before construction begins.
Once Through Cooling Regulations: State policy requiring shutdown of coastal power plants using ocean water cooling drives the 2029 Scattergood transition affecting western Los Angeles.
Peer Company Approaches
Most data center REITs that were previously public have been acquired by private equity firms:
- QTS Realty Trust: Acquired by Blackstone (August 2021, $10B)
- CyrusOne: Acquired by KKR/Global Infrastructure Partners (March 2022, $15B)
- CoreSite Realty: Acquired by American Tower (December 2021, $10.1B)
These acquisitions remove peer comparison data from public view. Equinix (EQIX) remains the primary publicly-traded peer, though with different business model focus on interconnection facilities rather than hyperscale wholesale properties.
Industry practice generally involves securing utility commitments before beginning construction, but California’s unprecedented demand growth has challenged traditional approaches. The question is whether DLR’s development-ahead-of-power model represents calculated risk-taking or departure from industry norms.
Timeline Observation
A notable pattern emerges in peer acquisition timing: QTS, CyrusOne, and CoreSite all went private between August 2021 and March 2022—removing three of four major publicly-traded data center REITs from public disclosure requirements. This consolidation preceded the period when California power constraints became widely documented in 2024-2025. Whether this timing reflects private equity recognition of emerging infrastructure risks or unrelated investment thesis is unclear from public information. Equinix remains the primary public comparable.
Research Questions for Further Investigation
The questions below are directed to journalists with investigative resources, securities regulators, and institutional investors with access to non-public information. Each question identifies specific information that would clarify whether observed patterns represent industry-wide infrastructure challenges or company-specific classification and disclosure issues:
Asset Classification and Valuation
- How does DLR classify SJC37 for financial reporting purposes: operating property, development in progress, or land held for development?
- What is the specific carrying value for SJC37 and other California power-constrained facilities?
- Has management performed impairment assessments on power-constrained facilities, and what were the results?
- How does DLR determine “recoverable amount” for facilities without confirmed power delivery dates?
Power Delivery and Risk Management
- Does DLR hold binding contractual commitments from Silicon Valley Power for SJC37 power delivery, or are 2028 timelines estimates?
- What due diligence procedures did DLR follow regarding power availability before beginning SJC37 construction?
- Has DLR secured backup power, alternative grid connections, or other contingency plans for LA facilities during the 2029 Scattergood transition?
- What economic analysis supports building facilities before power availability confirmation?
Disclosure and Investor Communication
- Has management discussed power-constrained facilities in earnings calls or investor presentations?
- What internal risk assessments exist regarding covenant compliance sensitivity to California power constraints?
- Has DLR conducted stress testing on covenant compliance under scenarios where power-constrained facilities require impairment recognition, and have results been shared with credit rating agencies and major institutional holders?
- What disclosure obligations apply when covenant margins reach the narrow levels documented here?
Industry Comparison
- How do other data center operators approach development in power-constrained markets?
- Are there industry benchmarks for acceptable timelines between construction completion and power delivery?
- What alternatives exist for monetizing or disposing of unpowered data center shells?
- How do lenders and credit rating agencies view facilities built ahead of power availability?
Conclusion
This analysis examines Digital Realty Trust’s California data center portfolio through publicly available documents, focusing on power delivery constraints and financial covenant implications. Three key findings emerge:
First, three of DLR’s four California facilities face documented power constraints, with SJC37 representing a completed building awaiting power for 6+ years and two Los Angeles facilities exposed to 2029 grid transition risks.
Second, scenario modeling based on Q3 2025 SEC filings shows DLR maintains only $300 million (1.1%) cushion above its unencumbered asset covenant requirement. Asset reclassifications or impairments affecting power-constrained facilities could trigger covenant breach.
Third, substantial information gaps exist regarding facility-level carrying values, power delivery contracts, impairment assessments, and alternative plans for affected properties.
The situation reflects broader infrastructure challenges facing California’s data center industry, where demand growth has outpaced grid capacity expansion. Additional investigation through detailed financial analysis, management inquiry, and comparison to peer practices would provide further insight into these issues.
The intersection of power-constrained facilities and minimal covenant cushion creates measurable financial risk that current disclosure practices may not adequately communicate to market participants.
Sources and References
All factual assertions in this analysis trace to the following primary sources:
SEC Filings:
- Digital Realty Q3 2025 10-Q (October 31, 2025)
- Digital Realty 8-K (September 30, 2024)
Municipal Records:
- Santa Clara Building Permits (641 Walsh Avenue)
Utility Documentation:
- Silicon Valley Power capacity statements (November 2024)
- LADWP Scattergood project documentation
- NREL Scattergood study
News Coverage:
- Bloomberg: “Data Centers in Nvidia’s Hometown Stand Empty Awaiting Power” (November 10, 2025)
- Fortune: “Nvidia’s hometown Santa Clara data centers empty power grid” (November 10, 2025)
- Mercury News: “Santa Clara nvidia data centers awaiting power” (November 10, 2025)
- Santa Clara Voice: “Data centers Santa Clara third largest general fund revenue generator”
- CalMatters: “Scattergood hydrogen crossroads LADWP” (October 2025)
Industry Resources:
Research Materials and Data
This analysis drew from extensive primary source research and the material is available (research document, spreadsheet) for verification, additional investigation, and programmatic analysis. Corrections can be sent to the email address below.
— Free to share, translate, use with attribution: D.T. Frankly (dtfrankly.com)
§